Interactions¶
This page documents the message flows that drive a contract through its lifecycle — the happy path, rework, timeouts, cancellation, and disputes. For the state diagram itself, see Contract Lifecycle.
Happy path¶
sequenceDiagram
participant A as Party A
participant Arb as Arbiter
participant B as Party B
A->>Arb: ① CONTRACT_CREATE
Arb->>B: ② notify for approval
B->>Arb: ③ CONTRACT_APPROVE
Arb->>A: ④ STATUS > PENDING
Arb->>B: ④ STATUS > PENDING
Arb->>A: ⑤ STATUS > ACTIVE
Arb->>B: ⑤ STATUS > ACTIVE
rect rgb(245, 245, 245)
Note over A,B: Arbiter steps aside — A and B communicate directly
A->>B: INVOKE
B->>A: INVOKE
end
B->>Arb: ⑥ CONTRACT_COMPLETE
Note over A,B: COMPLETING
Arb->>A: ⑦ request acceptance
A->>Arb: ⑧ CONTRACT_ACCEPT
Note over A,B: SETTLING
A->>Arb: ⑨ CONTRACT_RATE
alt ESCROW
Note over Arb: ⑩ internal transfer A → B
else DIRECT
Note over A,B: ⑩ external payment (see Payment)
end
Arb->>A: ⑪ STATUS > SETTLED
Arb->>B: ⑪ STATUS > SETTLED
The Arbiter is involved at every transition but not during execution itself — once ACTIVE, A and B talk directly with normal INVOKE messages.
Rework¶
After B submits, A may reject and request rework:
sequenceDiagram
participant A as Party A
participant Arb as Arbiter
participant B as Party B
B->>Arb: CONTRACT_COMPLETE
Note over A,B: COMPLETING
Arb->>A: request acceptance
A->>Arb: CONTRACT_REWORK
Arb->>A: STATUS > ACTIVE
Arb->>B: STATUS > ACTIVE
Note over A,B: B continues execution
B->>Arb: CONTRACT_COMPLETE
Note over A,B: COMPLETING
Arb->>A: request acceptance
A->>Arb: CONTRACT_ACCEPT
Note over A,B: SETTLING
Rework is capped by max_rework_count (default 3). Past the cap, the contract auto-transitions to DISPUTED — this prevents A from blocking B with unbounded revision requests.
Timeouts¶
The Arbiter enforces phase timeouts. These cannot be bypassed and they record a timeout event against the delaying party's reputation.
| Phase | Timeout | Arbiter action |
|---|---|---|
| DRAFT | counterparty doesn't respond | auto-CANCELLED |
| PENDING | A doesn't pay (ESCROW) / neither side confirms (DIRECT) | auto-CANCELLED |
| ACTIVE | B doesn't complete | auto-CANCELLED + refund A (ESCROW) |
| COMPLETING | A doesn't accept | treated as accepted → SETTLING |
| SETTLING (ESCROW) | B doesn't confirm receipt | auto-SETTLED (Arbiter has proof of payment) |
| SETTLING (DIRECT) | B doesn't confirm receipt | auto-DISPUTED (Arbiter cannot confirm on B's behalf) |
Cancellation¶
| Phase | Who can cancel | Behaviour |
|---|---|---|
| DRAFT | either side | direct CANCELLED |
| PENDING | either side | direct CANCELLED |
| ACTIVE | both sides agree | A requests cancel → Arbiter asks B to confirm → CANCELLED |
| ACTIVE | B alone | B abandons execution → CANCELLED; B's reputation is impacted |
| COMPLETING | not directly cancellable | only accept, rework, or dispute |
| SETTLING | not cancellable | payment failure / timeout → DISPUTED |
| DISPUTED | Arbiter decides | ESCROW: Arbiter refunds internally; DIRECT: no funds touched, recorded only |
Disputes¶
Disputes enter from several paths:
- From
COMPLETING— A requests rework repeatedly untilmax_rework_countis exceeded, or either side opens a dispute manually. - From
ACTIVE— A requests cancel and B refuses (or vice versa). - From
SETTLINGunder DIRECT — payment confirmation times out.
Once DISPUTED, the Arbiter resolves either by arbitrated settlement (release funds proportionally) or arbitrated cancellation (full refund). The exact resolution policy is still evolving; the current state machine has the transition but the resolution body is conservative.
Hard rejections¶
The Arbiter rejects these cases before they enter the flow at all:
| Scenario | Reason |
|---|---|
| A has insufficient balance | CONTRACT_FUND checks balance < amount |
| Self-contract | party_a == party_b |
| Amount ≤ 0 | contract amount must be positive |
| Contract with a non-existent entity | the Arbiter validates both addresses |
| Action by a non-party | only party_a / party_b may act on their contract |
| Action not allowed in the current state | e.g. rating after SETTLED, paying after CANCELLED |
A rejected message produces an ERROR reply and the contract state does not change.